Enterprise information

企业信息

Current location: Home > Enterprise information > Tongguan news

The main well of chambisi copper mine in Zambia contracted by the company broke 100 meters in March

datatime:2020-06-19

Since the normal construction of aquifer, the main shaft excavation and construction project of southeast orebody of Zhongse Africa Mining Co., Ltd. undertaken by the company has kept monthly well completion for more than 80 meters. In March 2014, the project department overcame the great change of geological conditions and abnormal power supply. Under the condition that the well depth has reached 600 meters, the monthly well completion of 101 meters has been realized. Zhongse Africa Mining Co., Ltd. and the supervision company have jointly submitted to the company Send a congratulatory letter.